Pipeline for $165 Billion Oracle Data Center Delayed to Next Year
August 14, 2026
The Green Chile pipeline that would fuel Oracle’s Project Jupiter data centre in New Mexico has been pushed from 15 August to 1 February 2027, according to a filing by Energy Transfer’s Transwestern unit. The state land commissioner has twice refused the route, citing water use and emissions.
The pipeline that would fuel Oracle’s largest planned data centre has slipped by nearly six months. Energy Transfer’s Transwestern unit told federal regulators on Friday that the Green Chile Project now has an in-service date of 1 February 2027, against a previous target of 15 August.
What it feeds is not a normal building. Project Jupiter in Doña Ana County is planned at 2.5 gigawatts, powered by Bloom Energy fuel cells, with Oracle as the tenant hosting AI infrastructure for OpenAI.